In the last week of September, we received a new inquiry from regular customer who stated that it would take 4 weeks for delivery, including anti-corrosion. We learned that the fast delivery is most important point for this order. Xinyue people responded the fastest.
Due to this order is for X52N PSL2 G high-grade seamless pipes, the stock quantity cannot meet the quantity of the entire order. With the strong resource integration ability of Xinyue, we found the production schedule of the steel pipe factory within 3 days and quickly organized new production. The customer arranges full process supervision from end customers, contractor customers, intermediate customers, and third parties from raw materials to the factory. During the supervision process of steel pipe production, they all witness the online UT test, Hydrostatic test, measurement test and so on, customers are very satisfied with the quality of the factory.
According to the production plan of the steel pipes, we have also coordinated the production line of the anti-corrosion factory to ensure that our steel pipes can be put online for anti-corrosion production as soon as they arrive at the anti-corrosion factory on the second day.
In the anti-corrosion factory, customers have conducted very strict inspections on every process of the factory, witness the holiday test, Pull test and so on.
We actually completed the anti-corrosion of all the pipes in less than 4 weeks. We highly appreciate our early delivery to customers, which It also laid a firm foundation for future cooperation.